Solar canopy decisions
Comparing Solar Carport Quotes: A 12-Point Scope Checklist
Compare solar carport quotations by aligning surveys, foundations, underground services, reinstatement, grid work and acceptance scope.

Compare scope before totals
Compare solar carport quotes against the same scope before comparing their totals. A frame package, a package with photovoltaic modules, and an installed electrical system can cover different work. Ask each bidder to state what is included, what is excluded and who handles the gaps.
Use this checklist when requesting a TTH solar canopy or comparing it with another proposal. It is a procurement worksheet, not a statement that TTH supplies every item listed. The written project quotation must define the actual supply and installation scope.
Label the package before comparing prices
Ask the bidder to describe the offer in plain terms. Does it cover the structure only, the structure with specified modules, or a defined installed system? If the quote uses “complete” or “turnkey,” request its inclusions and exclusions rather than relying on that label.
Keep optional batteries and EV charging separate from the base offer. A drawing showing those components does not confirm that they are priced, compatible with the proposed system or approved for the site.
Check these 12 items in every quotation
For each row, record Included, Provisional, Excluded or Unconfirmed. An unanswered item stays unconfirmed; do not treat it as included at no charge.
The checklist organizes questions; it does not allocate legal responsibility or specify how to build or wire the system. Confirm local requirements with the responsible designers, installers and authorities. DOE's PV procurement guidance supports reviewing site constraints and electrical infrastructure before procurement. It is US federal guidance, not a universal rule for every market.
| Item | Question for the bidder | Evidence to request |
|---|---|---|
| 1. Site information and surveys | Who checks the dimensions, ground conditions and buried services used for the proposal? | Survey scope, site inputs and outstanding investigations |
| 2. Structure and layout | Which frame and layout are priced, including post positions and clear vehicle height? | Identified configuration and drawing revision |
| 3. Foundations and anchors | Are foundation design, excavation, concrete and anchors included? What site assumptions remain? | Scope breakdown and the responsible designer's required inputs |
| 4. Modules and roof interfaces | Are modules included? Who confirms their model, mounting arrangement and any rain-shedding details? | Component schedule and coordinated roof/interface drawings |
| 5. Inverter and electrical equipment | Which equipment is supplied, and who checks the design for the intended site and use? | Equipment schedule and electrical design scope |
| 6. Cable routes and electrical installation | Who supplies and installs the wiring, supports, protection and earthing/bonding arrangements? | Defined work boundary and drawings from the responsible qualified parties |
| 7. Drainage and surface reinstatement | Who handles runoff, repairs disturbed paving and restores parking markings? | Drainage and reinstatement scope tied to the site plan |
| 8. Delivery and lifting | Where does delivery end? Who unloads, stores and lifts the components? | Delivery terms, site-access assumptions and handling responsibilities |
| 9. Approvals and grid connection | Who handles the applicable applications, utility coordination, metering and any required upgrades? | Responsibility schedule, utility information and known exclusions |
| 10. Batteries and EV charging | Are these included options or future provisions? What equipment and integration work are actually priced? | Separate option schedule and system-design scope |
| 11. Testing and handover | Who tests the finished work and supplies the drawings, manuals and acceptance records? | Agreed test/acceptance scope and handover-document list |
| 12. Warranty and after-sales work | Which party covers each supplied component and installation work? How are faults reported across suppliers? | Written warranty scope, exclusions and support contacts |
Agree what must be confirmed before foundation work
Ask each bidder to separate what it needs to price the foundations from what the project team must confirm before excavation. Where the quotation assumes an available work area, known underground services or a particular finished surface level, record that assumption alongside the named party and the drawing or survey that will confirm it. A line marked “foundations included” does not answer any of those questions by itself.
Use two checkpoints in the comparison: one for excavation and one for the foundation-to-frame handover. This helps distinguish a gap in the quoted scope from an item that is included but still waiting for site information.
- Before excavation, ask who confirms the current layout, site and underground-service information, and any permissions needed to access or close the work area. Record unresolved items before agreeing a start date.
- Before handing over to the frame installer, ask which drawing revision the civil team used, who records the as-built anchor positions and levels, and who reviews any discrepancy before frame delivery or installation.
- Agree how a discovered service, changed level or anchor discrepancy affects the scope, price and schedule. For example, if a proposed post position conflicts with an existing service, ask for a coordinated drawing revision and written confirmation of who covers the change before committing to that layout.
Put an owner and a document beside each open item
A tick in an “included” column is only a starting point. Add the party responsible for the next action and the document that supports the answer. Use the same drawing revision across the offers.
These examples contain no project prices and assign no real contractor. Where an allowance is provisional, ask what it covers and what changes the final amount. Do not invent an amount to fill an empty cell.
| Item | Quote status | Responsible party | Evidence / revision | Next action |
|---|---|---|---|---|
| Paving reinstatement, example only | Excluded | To be confirmed by the buyer | Bidder's exclusion list | Obtain a separate scope and price |
| Grid upgrade, example only | Unconfirmed | Project electrical team to coordinate with utility | Utility response pending | Confirm requirements before treating the quote as a complete budget |
| Your project item | Included / Provisional / Excluded / Unconfirmed | Named party | Document and date | Action and agreed due date |
Compare the same scope, then the commercial terms
Suppose one proposal includes paving repairs and another ends after the foundations are completed. Request a price for the missing work, or show it separately as an unresolved budget item. The lower quoted total alone cannot establish the lower cost of the completed project.
Check currency and delivery terms alongside taxes or duties stated in each offer. Record quotation validity and payment milestones. And keep equipment options outside the base comparison until both offers use the same assumptions.
If structure and PV installation are under separate contracts, use the split-contract interface guide to assign design changes and approval at their boundaries. This quotation checklist identifies missing scope; the interface guide deals with how the parties coordinate it.
Agree what counts as completion
Ask for the handover documents and acceptance process before ordering. Physical construction, electrical testing and permission for connected operation can be separate steps. The applicable sequence depends on the project and local utility requirements.
DOE's installation and commissioning guidance discusses inspection and commissioning records. Its interconnection checklist provides questions for utility coordination. Use them as planning references, not as evidence that a particular TTH project has been approved.
Send a clearer quotation request
Provide the project country and site plan, intended parking layout and any known electrical requirements. State whether you want the canopy structure quoted separately from the PV and electrical work. Ask TTH to identify its proposed supply boundary and list the information still needed.
Keep the returned quotation, drawing revision and open-item register together. The next useful step is to resolve the entries that could change the scope, rather than asking for a firmer total on an incomplete brief.
Can I compare quotes directly when the covered area and stated PV capacity match?
First compare the work included. Foundations, delivery, electrical installation, surface repairs and connection work may differ. Matching area and stated capacity do not establish matching project scope. Use the same checklist for each bidder and retain unconfirmed items visibly.
More questions, practical answers →